ABB’s Ampang (AMG) Line Existing & Line Extension

ABB’s Ampang (AMG) Line Existing & Line Extension :
Testing & Commissioning Power Distribution System

Our task

Global Power Test (GPT) was engaged for Installation/TOC/PICO/SAT/Snag lists for Switch gear, Control & Relay Panel, Distribution boards, Battery(Fuse box & Charger Panel), Traction(Transmission, Rectification panels, Isolation & Earth Switch), RTU & SCADA, and Cabling(Control cable, Fiber Optic testing)

Our engineering deliverables included:

  • Finalization of T&C program, Survey of site & review of technical requirements.
  • Test Equipment in accordance with Local and International Standards.
  • Creating Test Plan and Submission of the test reports and records for all the test phases from start to until the train runs successfully. Preparation and approval of Test Documentation.
  • Implementation of tests and requirements coordination with Operation.
  • Input to the client’s Commissioning Plan, including Method Statements, Inspection and Test Plan and execution schedule.
  • Input to the client’s Completions Dossier, including Inspection and Test Records and as-built documentation.

Our field works included:

  • Generation of HSSE packs including Safe Work Method Statements, Permits to Work and compliance with the end-user’s site induction requirements.
  • Testing & Commissioning of all the Equipment in the Bill of Quantity – Implementation, download and test of Software.

Our Action:

  • Agreed with the client on the scope of work.
  • Designed an action plan for leveraging our knowledge of the end-users systems and requirements to meet the planning gateways within half the normal time allowed.
  • Quickly allocated and deployed T & C Engineers and GPT resources as required to maintain close integration with the client and end-user during the planning and implementation phases.
  • Structured our field team to respond quickly and efficiently to ad-hoc Testing & Commissioning schedule and scope changes.

Result:

  • High quality deliverables achieved within the tight lead time.
  • All the Tests were fully carried out within the time allocated
  • Completion of test documentation and As-Built documentation required for the Completion dossier
  • The client has demonstrated their satisfaction with our services by engaging GPT for other works and has issued the “Best HSE performed Subcontractor”, for the year 2016